Share to:

As a specialist in the management of Capital Improvement Programs, we find that the question most frequently raised by stakeholders concerns the progression of each project in a Capital Improvement Bond Program. Every project navigates through distinct phases – the design phase, right-of-way (ROW) acquisition, the repositioning of utilities, and finally, construction. It is essential to understand that the time each phase requires can vary substantially, influenced by the scale, intricacy, and nature of the project at hand. Nevertheless, we are equipped to offer indicative timelines derived from established industry standards.

Transportation Infrastructure: For road, highway, and bridge projects, the design phase often lasts between one and three years. ROW acquisition may take another six months to two years, especially for more complex projects or those facing legal hurdles. Utilities relocation can also take between six months and two years. The construction phase generally spans one to three years, depending on project size and complexity.

Utility Systems: Water, sewage, and other utility system projects typically have a design phase of six months to two years. ROW acquisition and utility relocation can add another year, particularly for large-scale projects or those in densely populated areas. Construction usually takes one to three years.

Public Buildings and Facilities: The design phase for these projects can range from one to three years, with ROW acquisition usually taking six months to a year. Utilities relocation might take another six months to a year. Construction of large buildings, such as schools or hospitals, typically takes two to four years.

Parks and Recreation: For park and recreational facility projects, the design phase generally lasts six months to a year. ROW acquisition, if necessary, can take an additional six months to a year, and utilities relocation can add another three to six months. Construction generally lasts one to two years.

Public Safety Infrastructure: The design phase for these projects usually lasts one to two years. ROW acquisition and utility relocation might each add another six months to a year. The construction phase typically takes one to three years, depending on the project’s scale and complexity.

Environmental and Sustainability Projects: These projects typically have a design phase of one to two years. ROW acquisition and utilities relocation can each add another six months to a year. Construction often spans one to three years.

Affordable Housing: Design of these projects generally lasts one to two years. ROW acquisition and utility relocation may each add another six months to a year. Construction for affordable housing typically ranges from one to three years.

Please note that these timelines are estimates and the actual durations can vary significantly depending on numerous factors, including the project’s complexity, the presence of unforeseen complications, weather conditions, regulatory hurdles, community feedback, and more.

Transportation Infrastructure (Roads, Highways, Bridges)

Design: 1-3 years
Right-of-Way Acquisition: 6 months – 2 years
Utilities Relocation: 6 months – 2 years
Construction: 1-3 years
Minimum Duration: 3.5 years
Maximum Duration: 10 years

Utility Systems (Water, Sewage, Electricity, Gas, Telecommunications)

Design: 6 months – 2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 2.5 years
Maximum Duration: 7 years

Public Buildings and Facilities (Schools, Libraries, Hospitals, Administrative Buildings)

Design: 1-3 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 2-4 years
Minimum Duration: 3.5 years
Maximum Duration: 9 years

Parks and Recreation (Parks, Community Centers, Sports Complexes)

Design: 6 months – 1 year
Right-of-Way Acquisition: 6 months – 1 year (if necessary)
Utilities Relocation: 3-6 months
Construction: 1-2 years
Minimum Duration: 2 years
Maximum Duration: 5 years

Public Safety Infrastructure (Emergency Response Systems, Fire Safety Systems)

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

Environmental and Sustainability Projects (Renewable Energy, Water Conservation, Waste Management)

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

Affordable Housing

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

These total durations are estimates based on the individual stage durations previously provided. They represent a cumulative timeframe that incorporates design, right-of-way acquisition, utilities relocation, and construction. As previously noted, actual durations can vary significantly depending on a multitude of factors specific to each project.

At Front Line Advisory Group, we are pioneers in Capital Improvement Bond Management, leveraging unparalleled expertise and deep industry insights. Our mission extends beyond consultation – we empower our clients to realize the full potential of their investments, ensuring tax dollars are put to maximum use through astute Program Management Consulting. For more information or to commence your journey towards transformative bond management, reach out to us at info@frontlineadvisorygroup.com

FLAG provides program management consulting services in Central Texas for municipal and school capital improvement bonds. FLAG is revolutionizing the construction industry and transforming client expectations by obsessing over the basics of budget oversight, schedule enforcement, compliance, vendor management, and stakeholder communication.

Join our weekly newsletter and receive a free copy of our new book!

JOIN NEWSLETTER

Articles Bonds Capital Improvement Programs Planning

Strategic Planning for Capital Infrastructure Bond Packages Amid Economic Challenges

In light of the emerging economic landscape punctuated by escalating interest rates, heightened inflation, and labor and logistical shortages, municipalities...
Read More
Articles Bonds Capital Improvement Programs Planning Process Improvement Schedule

Unraveling the Complexities: A Deeper Examination of Overruns in Capital Infrastructure Bond Projects

Capital infrastructure bonds are pivotal financial instruments for ambitious public projects. However, the recurring theme of these ventures overshooting both...
Read More
Articles Bonds Planning

Navigating a Bond Program through the Maze of a Rising Interest Rate Environment: An Effective Guide

The specter of rising interest rates often casts a long shadow over municipalities, especially when it comes to managing capital...
Read More
Articles Bonds Process Improvement

The Legacy Park Debacle: Unraveling the Pitfalls of Conduit Bonds and Ways to Sidestep Them

The world of municipal bonds, long considered a safe haven for investors, has recently been jolted by an unfolding saga...
Read More
Articles Capital Improvement Programs CIP Schedule

Understanding Capital Improvement Project Timelines

As a specialist in the management of Capital Improvement Programs, we find that the question most frequently raised by stakeholders...
Read More
Articles Bonds Capital Improvement Programs

Managing a Construction Manager within a Capital Improvement Bond Program: A Guide for Government Agencies

As municipalities map out their long-term infrastructural blueprints, capital improvement bond programs emerge as paramount in the funding ecosystem. These...
Read More
Articles Bonds Capital Improvement Programs CIP CIP Budgetting Economic Development

Future-Proofing Your Municipality

Effective local service delivery underpins all thriving Texan communities. As municipalities across the State of Texas seek innovative avenues to...
Read More
Articles Bonds Capital Improvement Programs Taxes

The Importance for Taxpayers of Well-Managed Capital Infrastructure Bond Programs

The bedrock of public funding, taxpayers, must be actively invested in the management of capital infrastructure bond programs. The programs'...
Read More
Articles Bonds Capital Improvement Programs Local

Texas Unveils $142 Billion Transportation Infrastructure Investment with Major Allocations for Austin

In a groundbreaking move to boost Texas' transportation infrastructure, Gov. Greg Abbott announced on Aug. 17 a massive $142 billion...
Read More
Articles Bonds Capital Improvement Programs Schedule

What are the most common reasons capital infrastructure projects go over schedule? What can I do to make it stop!

Capital infrastructure projects, the backbone of any thriving metropolis or region, often face unexpected delays that can trigger a domino...
Read More
1 7 8 9 10 11 19