Share to:

As a specialist in the management of Capital Improvement Programs, we find that the question most frequently raised by stakeholders concerns the progression of each project in a Capital Improvement Bond Program. Every project navigates through distinct phases – the design phase, right-of-way (ROW) acquisition, the repositioning of utilities, and finally, construction. It is essential to understand that the time each phase requires can vary substantially, influenced by the scale, intricacy, and nature of the project at hand. Nevertheless, we are equipped to offer indicative timelines derived from established industry standards.

Transportation Infrastructure: For road, highway, and bridge projects, the design phase often lasts between one and three years. ROW acquisition may take another six months to two years, especially for more complex projects or those facing legal hurdles. Utilities relocation can also take between six months and two years. The construction phase generally spans one to three years, depending on project size and complexity.

Utility Systems: Water, sewage, and other utility system projects typically have a design phase of six months to two years. ROW acquisition and utility relocation can add another year, particularly for large-scale projects or those in densely populated areas. Construction usually takes one to three years.

Public Buildings and Facilities: The design phase for these projects can range from one to three years, with ROW acquisition usually taking six months to a year. Utilities relocation might take another six months to a year. Construction of large buildings, such as schools or hospitals, typically takes two to four years.

Parks and Recreation: For park and recreational facility projects, the design phase generally lasts six months to a year. ROW acquisition, if necessary, can take an additional six months to a year, and utilities relocation can add another three to six months. Construction generally lasts one to two years.

Public Safety Infrastructure: The design phase for these projects usually lasts one to two years. ROW acquisition and utility relocation might each add another six months to a year. The construction phase typically takes one to three years, depending on the project’s scale and complexity.

Environmental and Sustainability Projects: These projects typically have a design phase of one to two years. ROW acquisition and utilities relocation can each add another six months to a year. Construction often spans one to three years.

Affordable Housing: Design of these projects generally lasts one to two years. ROW acquisition and utility relocation may each add another six months to a year. Construction for affordable housing typically ranges from one to three years.

Please note that these timelines are estimates and the actual durations can vary significantly depending on numerous factors, including the project’s complexity, the presence of unforeseen complications, weather conditions, regulatory hurdles, community feedback, and more.

Transportation Infrastructure (Roads, Highways, Bridges)

Design: 1-3 years
Right-of-Way Acquisition: 6 months – 2 years
Utilities Relocation: 6 months – 2 years
Construction: 1-3 years
Minimum Duration: 3.5 years
Maximum Duration: 10 years

Utility Systems (Water, Sewage, Electricity, Gas, Telecommunications)

Design: 6 months – 2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 2.5 years
Maximum Duration: 7 years

Public Buildings and Facilities (Schools, Libraries, Hospitals, Administrative Buildings)

Design: 1-3 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 2-4 years
Minimum Duration: 3.5 years
Maximum Duration: 9 years

Parks and Recreation (Parks, Community Centers, Sports Complexes)

Design: 6 months – 1 year
Right-of-Way Acquisition: 6 months – 1 year (if necessary)
Utilities Relocation: 3-6 months
Construction: 1-2 years
Minimum Duration: 2 years
Maximum Duration: 5 years

Public Safety Infrastructure (Emergency Response Systems, Fire Safety Systems)

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

Environmental and Sustainability Projects (Renewable Energy, Water Conservation, Waste Management)

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

Affordable Housing

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

These total durations are estimates based on the individual stage durations previously provided. They represent a cumulative timeframe that incorporates design, right-of-way acquisition, utilities relocation, and construction. As previously noted, actual durations can vary significantly depending on a multitude of factors specific to each project.

At Front Line Advisory Group, we are pioneers in Capital Improvement Bond Management, leveraging unparalleled expertise and deep industry insights. Our mission extends beyond consultation – we empower our clients to realize the full potential of their investments, ensuring tax dollars are put to maximum use through astute Program Management Consulting. For more information or to commence your journey towards transformative bond management, reach out to us at info@frontlineadvisorygroup.com

FLAG provides program management consulting services in Central Texas for municipal and school capital improvement bonds. FLAG is revolutionizing the construction industry and transforming client expectations by obsessing over the basics of budget oversight, schedule enforcement, compliance, vendor management, and stakeholder communication.

Join our weekly newsletter and receive a free copy of our new book!

JOIN NEWSLETTER

Articles Capital Improvement Programs CIP Economic Development

Building Better Communities: An Introduction to Successful Municipal Grant Writing

Writing grants for municipal projects is a critical function of local governmental planners that can lead to significant advancements in...
Read More
Articles Capital Improvement Programs CIP CIP Budgetting

‘Quick Wins’ in Capital Improvement Programs: A Catalyst for Voter Confidence and Stakeholder Support

Capital Improvement Programs (CIPs) hold an integral position in the strategic planning and development initiatives of our communities. They incorporate...
Read More
Articles Capital Improvement Programs CIP CIP Budgetting

The Art of Planning: A Comprehensive Guide to Creating a Capital Improvement Program Plan

In an era of rapid development and technological advancements, the thoughtful management of capital assets is more crucial than ever....
Read More
Articles Capital Improvement Programs CIP CIP Budgetting

A Comparative Analysis: Construction Manager vs. Construction Manager at Risk in Capital Improvement Projects

As urbanization and development continue to rise globally, understanding the various roles in construction becomes increasingly important. This blog post...
Read More
Articles Development Services Economic Development

Fueling Tomorrow: Leveraging Federal and Texas State Resources to Fund Economic Development

Texas Economic Development Corporations (EDCs) play an outsized role in driving economic growth and prosperity in their respective cities and...
Read More
Articles Economic Development

Driving Growth in Texas: The Role of Economic Development Corporations

In the dynamic landscape of community development, municipalities often turn to Economic Development Corporations (EDCs) as instrumental tools to foster...
Read More
Articles Economic Development

From Marketing to Small Business Support: How Economic Development Corporations Partner to Foster Growth

Economic Development Corporations (EDCs) in Texas are a key tool for local governments to attract businesses to both rural areas...
Read More
Articles Bonds Capital Improvement Programs CIP ISD

Unleashing Technological Potential: How Front Line Advisory Group is Changing the Game in Capital Improvement Program Management

On May 6th, 2023 Central Texas cities, counties, and school districts voted to support $4 Billion in infrastructure projects, school...
Read More
Articles Bonds CIP Budgetting Planning

The Texas Bond Review Board: An Essential Steward of the State’s Financial Health

As the Lone Star State's public finance community steers the course of our future, it's vital that we understand the...
Read More
Articles Development Services Planning Process Improvement

Improving Development Permit Approval Times: Cutting Red Tape with Effective Staff Analysis

As municipalities grapple with the new challenges posed by new permitting legislation recently initiated by the state of Texas, managers...
Read More
1 8 9 10 11 12 18