Share to:

As a specialist in the management of Capital Improvement Programs, we find that the question most frequently raised by stakeholders concerns the progression of each project in a Capital Improvement Bond Program. Every project navigates through distinct phases – the design phase, right-of-way (ROW) acquisition, the repositioning of utilities, and finally, construction. It is essential to understand that the time each phase requires can vary substantially, influenced by the scale, intricacy, and nature of the project at hand. Nevertheless, we are equipped to offer indicative timelines derived from established industry standards.

Transportation Infrastructure: For road, highway, and bridge projects, the design phase often lasts between one and three years. ROW acquisition may take another six months to two years, especially for more complex projects or those facing legal hurdles. Utilities relocation can also take between six months and two years. The construction phase generally spans one to three years, depending on project size and complexity.

Utility Systems: Water, sewage, and other utility system projects typically have a design phase of six months to two years. ROW acquisition and utility relocation can add another year, particularly for large-scale projects or those in densely populated areas. Construction usually takes one to three years.

Public Buildings and Facilities: The design phase for these projects can range from one to three years, with ROW acquisition usually taking six months to a year. Utilities relocation might take another six months to a year. Construction of large buildings, such as schools or hospitals, typically takes two to four years.

Parks and Recreation: For park and recreational facility projects, the design phase generally lasts six months to a year. ROW acquisition, if necessary, can take an additional six months to a year, and utilities relocation can add another three to six months. Construction generally lasts one to two years.

Public Safety Infrastructure: The design phase for these projects usually lasts one to two years. ROW acquisition and utility relocation might each add another six months to a year. The construction phase typically takes one to three years, depending on the project’s scale and complexity.

Environmental and Sustainability Projects: These projects typically have a design phase of one to two years. ROW acquisition and utilities relocation can each add another six months to a year. Construction often spans one to three years.

Affordable Housing: Design of these projects generally lasts one to two years. ROW acquisition and utility relocation may each add another six months to a year. Construction for affordable housing typically ranges from one to three years.

Please note that these timelines are estimates and the actual durations can vary significantly depending on numerous factors, including the project’s complexity, the presence of unforeseen complications, weather conditions, regulatory hurdles, community feedback, and more.

Transportation Infrastructure (Roads, Highways, Bridges)

Design: 1-3 years
Right-of-Way Acquisition: 6 months – 2 years
Utilities Relocation: 6 months – 2 years
Construction: 1-3 years
Minimum Duration: 3.5 years
Maximum Duration: 10 years

Utility Systems (Water, Sewage, Electricity, Gas, Telecommunications)

Design: 6 months – 2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 2.5 years
Maximum Duration: 7 years

Public Buildings and Facilities (Schools, Libraries, Hospitals, Administrative Buildings)

Design: 1-3 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 2-4 years
Minimum Duration: 3.5 years
Maximum Duration: 9 years

Parks and Recreation (Parks, Community Centers, Sports Complexes)

Design: 6 months – 1 year
Right-of-Way Acquisition: 6 months – 1 year (if necessary)
Utilities Relocation: 3-6 months
Construction: 1-2 years
Minimum Duration: 2 years
Maximum Duration: 5 years

Public Safety Infrastructure (Emergency Response Systems, Fire Safety Systems)

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

Environmental and Sustainability Projects (Renewable Energy, Water Conservation, Waste Management)

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

Affordable Housing

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

These total durations are estimates based on the individual stage durations previously provided. They represent a cumulative timeframe that incorporates design, right-of-way acquisition, utilities relocation, and construction. As previously noted, actual durations can vary significantly depending on a multitude of factors specific to each project.

At Front Line Advisory Group, we are pioneers in Capital Improvement Bond Management, leveraging unparalleled expertise and deep industry insights. Our mission extends beyond consultation – we empower our clients to realize the full potential of their investments, ensuring tax dollars are put to maximum use through astute Program Management Consulting. For more information or to commence your journey towards transformative bond management, reach out to us at info@frontlineadvisorygroup.com

FLAG provides program management consulting services in Central Texas for municipal and school capital improvement bonds. FLAG is revolutionizing the construction industry and transforming client expectations by obsessing over the basics of budget oversight, schedule enforcement, compliance, vendor management, and stakeholder communication.

Join our weekly newsletter and receive a free copy of our new book!

JOIN NEWSLETTER

Articles Capital Improvement Programs CIP CIP Budgetting

Effective Planning: El Paso County’s Consideration of a $200 Million Bond Program

Navigating the intricate dynamics of public infrastructure development often requires a careful blend of foresight, strategy, and community engagement. A...
Read More
Articles Capital Improvement Programs CIP CIP Budgetting

What is a Capital Improvement Program Readiness Audit (CIPRA)

The requirement for a Capital Improvement Program Readiness Audit (CIPRA), while not universally mandated, is of paramount importance to ensure...
Read More
Articles Capital Improvement Programs CIP CIP Budgetting Local

Understanding the Difference Between Critical Path and Driving Path in Project Schedules

Project management involves meticulous planning and scheduling to ensure the successful completion of a project within the allotted time frame....
Read More
Articles Capital Improvement Programs CIP CIP Budgetting

Going Beyond Finance: The Need for Comprehensive Preapproval Processes for Bond Underwriters in High-Growth Municipalities and Independent School Districts

Public finance is an intricate and multi-faceted domain. Its complexity becomes pronounced when we consider the case of bond underwriters...
Read More
Articles Local

Texas: A 5 Year Examination of the Bonds Issued by ISDs and Local Governments

Over the course of the past five years (The period is November 2018 - May 2023), Texas has seen local...
Read More
Articles Local

How to incorporate AI into the Budget Process: A focus on Local Governments

Incorporating artificial intelligence (AI) into the budgeting process in local governments can greatly enhance efficiency, accuracy, and informed decision-making. This...
Read More
Articles Bonds ISD School Bonds

The Changing Landscape of School District Bond Propositions

In the intricate labyrinth of legislation, changes to bond propositions have introduced new complexities for school districts, specifically in how...
Read More
Articles Change Management

Unfreezing the Status Quo

Strategies for Implementing the Unfreeze Phase of Change Management Change is a constant in today's rapidly evolving business landscape. Organizations...
Read More
Articles Capital Improvement Programs CIP

A Prerequisite for Progress: The importance of a Readiness Audit for Capital Improvement Bond Programs

As financial stewards of taxpayers' dollars, local government entities and educational institutions have a solemn duty towards citizens to ensure...
Read More
Articles CIP CIP Budgetting

Understanding the Bonds: Voter-Approved vs. Certificates of Obligation

The world of municipal financing can often be complex, but it is vital for taxpayers to understand the key differences...
Read More
1 9 10 11 12 13 18