Share to:

As a specialist in the management of Capital Improvement Programs, we find that the question most frequently raised by stakeholders concerns the progression of each project in a Capital Improvement Bond Program. Every project navigates through distinct phases – the design phase, right-of-way (ROW) acquisition, the repositioning of utilities, and finally, construction. It is essential to understand that the time each phase requires can vary substantially, influenced by the scale, intricacy, and nature of the project at hand. Nevertheless, we are equipped to offer indicative timelines derived from established industry standards.

Transportation Infrastructure: For road, highway, and bridge projects, the design phase often lasts between one and three years. ROW acquisition may take another six months to two years, especially for more complex projects or those facing legal hurdles. Utilities relocation can also take between six months and two years. The construction phase generally spans one to three years, depending on project size and complexity.

Utility Systems: Water, sewage, and other utility system projects typically have a design phase of six months to two years. ROW acquisition and utility relocation can add another year, particularly for large-scale projects or those in densely populated areas. Construction usually takes one to three years.

Public Buildings and Facilities: The design phase for these projects can range from one to three years, with ROW acquisition usually taking six months to a year. Utilities relocation might take another six months to a year. Construction of large buildings, such as schools or hospitals, typically takes two to four years.

Parks and Recreation: For park and recreational facility projects, the design phase generally lasts six months to a year. ROW acquisition, if necessary, can take an additional six months to a year, and utilities relocation can add another three to six months. Construction generally lasts one to two years.

Public Safety Infrastructure: The design phase for these projects usually lasts one to two years. ROW acquisition and utility relocation might each add another six months to a year. The construction phase typically takes one to three years, depending on the project’s scale and complexity.

Environmental and Sustainability Projects: These projects typically have a design phase of one to two years. ROW acquisition and utilities relocation can each add another six months to a year. Construction often spans one to three years.

Affordable Housing: Design of these projects generally lasts one to two years. ROW acquisition and utility relocation may each add another six months to a year. Construction for affordable housing typically ranges from one to three years.

Please note that these timelines are estimates and the actual durations can vary significantly depending on numerous factors, including the project’s complexity, the presence of unforeseen complications, weather conditions, regulatory hurdles, community feedback, and more.

Transportation Infrastructure (Roads, Highways, Bridges)

Design: 1-3 years
Right-of-Way Acquisition: 6 months – 2 years
Utilities Relocation: 6 months – 2 years
Construction: 1-3 years
Minimum Duration: 3.5 years
Maximum Duration: 10 years

Utility Systems (Water, Sewage, Electricity, Gas, Telecommunications)

Design: 6 months – 2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 2.5 years
Maximum Duration: 7 years

Public Buildings and Facilities (Schools, Libraries, Hospitals, Administrative Buildings)

Design: 1-3 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 2-4 years
Minimum Duration: 3.5 years
Maximum Duration: 9 years

Parks and Recreation (Parks, Community Centers, Sports Complexes)

Design: 6 months – 1 year
Right-of-Way Acquisition: 6 months – 1 year (if necessary)
Utilities Relocation: 3-6 months
Construction: 1-2 years
Minimum Duration: 2 years
Maximum Duration: 5 years

Public Safety Infrastructure (Emergency Response Systems, Fire Safety Systems)

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

Environmental and Sustainability Projects (Renewable Energy, Water Conservation, Waste Management)

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

Affordable Housing

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

These total durations are estimates based on the individual stage durations previously provided. They represent a cumulative timeframe that incorporates design, right-of-way acquisition, utilities relocation, and construction. As previously noted, actual durations can vary significantly depending on a multitude of factors specific to each project.

At Front Line Advisory Group, we are pioneers in Capital Improvement Bond Management, leveraging unparalleled expertise and deep industry insights. Our mission extends beyond consultation – we empower our clients to realize the full potential of their investments, ensuring tax dollars are put to maximum use through astute Program Management Consulting. For more information or to commence your journey towards transformative bond management, reach out to us at info@frontlineadvisorygroup.com

FLAG provides program management consulting services in Central Texas for municipal and school capital improvement bonds. FLAG is revolutionizing the construction industry and transforming client expectations by obsessing over the basics of budget oversight, schedule enforcement, compliance, vendor management, and stakeholder communication.

Join our weekly newsletter and receive a free copy of our new book!

JOIN NEWSLETTER

Articles CIP

Capital Improvement Bond Election Victory: The Next Steps for Your Municipality

Understanding Capital Improvement Bonds So, your municipality just won a capital improvement bond election, and you're probably wondering what happens...
Read More
Articles CIP Planning Technology

The role of technology in accelerating the planning phase of construction projects in bond programs: A brief introduction

When it comes to bond programs for municipalities, the planning phase of construction projects can be a lengthy and challenging...
Read More
Articles School Bonds

Making an Informed Choice: School Bond Details Every Voter Should Know

What is the purpose of your school bond, and the implication of it not being approved? Taxpayers should understand what...
Read More
Articles Taxes

Making Sense of Your Surging Home Tax Appraisal and What You Can Do About It

Despite the recent decline in median home prices across Texas, the latest tax appraisals reveal that, on average, property values...
Read More
Articles CIP Schedule

How Project Controls, Specifically Schedule Management, Impact The Design Phase of Construction

Introduction Project controls, including schedule management, are essential to construction projects' success, ensuring they are delivered on time, on budget,...
Read More
Articles School Bonds

Why School Bonds Matter: 10 Key Reasons to Vote Yes, Whether You Have Kids or Not

In today's complex society, it is crucial for every citizen to stay informed about local politics and take part in...
Read More
Articles School Bonds

How Texas Property Value Studies Impact School District Funding and Taxes

Introduction Property value studies are essential for ensuring that school districts receive equitable funding for public education. The Texas Comptroller...
Read More
Articles CIP Budgetting

Comprehensive Cost Estimation in Design Processes: Contingency, Timing, Interest Rates, Inflation, and Factors to Consider for Capital Improvement Projects

Capital improvement projects (CIPs) are investments in the long-term development of an organization's infrastructure or facilities. These projects often involve...
Read More
Articles CIP Budgetting

The Real Reasons Why Construction Projects Always Seem To Go Over Budget

Let's say it outright: we almost always underestimate the costs! So why not fix this consistent issue and be done...
Read More
Articles Capital Improvement Programs

Mitigating the Effects of Surging Interest Rates on Capital Improvement Programs

Capital improvement programs (CIPs) play a critical role in the progress and modernization of societies. These initiatives necessitate substantial investments,...
Read More
1 13 14 15 16 17 18