As a specialist in the management of Capital Improvement Programs, we find that the question most frequently raised by stakeholders concerns the progression of each project in a Capital Improvement Bond Program. Every project navigates through distinct phases – the design phase, right-of-way (ROW) acquisition, the repositioning of utilities, and finally, construction. It is essential to understand that the time each phase requires can vary substantially, influenced by the scale, intricacy, and nature of the project at hand. Nevertheless, we are equipped to offer indicative timelines derived from established industry standards.

Transportation Infrastructure: For road, highway, and bridge projects, the design phase often lasts between one and three years. ROW acquisition may take another six months to two years, especially for more complex projects or those facing legal hurdles. Utilities relocation can also take between six months and two years. The construction phase generally spans one to three years, depending on project size and complexity.

Utility Systems: Water, sewage, and other utility system projects typically have a design phase of six months to two years. ROW acquisition and utility relocation can add another year, particularly for large-scale projects or those in densely populated areas. Construction usually takes one to three years.

Public Buildings and Facilities: The design phase for these projects can range from one to three years, with ROW acquisition usually taking six months to a year. Utilities relocation might take another six months to a year. Construction of large buildings, such as schools or hospitals, typically takes two to four years.

Parks and Recreation: For park and recreational facility projects, the design phase generally lasts six months to a year. ROW acquisition, if necessary, can take an additional six months to a year, and utilities relocation can add another three to six months. Construction generally lasts one to two years.

Public Safety Infrastructure: The design phase for these projects usually lasts one to two years. ROW acquisition and utility relocation might each add another six months to a year. The construction phase typically takes one to three years, depending on the project’s scale and complexity.

Environmental and Sustainability Projects: These projects typically have a design phase of one to two years. ROW acquisition and utilities relocation can each add another six months to a year. Construction often spans one to three years.

Affordable Housing: Design of these projects generally lasts one to two years. ROW acquisition and utility relocation may each add another six months to a year. Construction for affordable housing typically ranges from one to three years.

Please note that these timelines are estimates and the actual durations can vary significantly depending on numerous factors, including the project’s complexity, the presence of unforeseen complications, weather conditions, regulatory hurdles, community feedback, and more.

Transportation Infrastructure (Roads, Highways, Bridges)

Design: 1-3 years
Right-of-Way Acquisition: 6 months – 2 years
Utilities Relocation: 6 months – 2 years
Construction: 1-3 years
Minimum Duration: 3.5 years
Maximum Duration: 10 years

Utility Systems (Water, Sewage, Electricity, Gas, Telecommunications)

Design: 6 months – 2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 2.5 years
Maximum Duration: 7 years

Public Buildings and Facilities (Schools, Libraries, Hospitals, Administrative Buildings)

Design: 1-3 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 2-4 years
Minimum Duration: 3.5 years
Maximum Duration: 9 years

Parks and Recreation (Parks, Community Centers, Sports Complexes)

Design: 6 months – 1 year
Right-of-Way Acquisition: 6 months – 1 year (if necessary)
Utilities Relocation: 3-6 months
Construction: 1-2 years
Minimum Duration: 2 years
Maximum Duration: 5 years

Public Safety Infrastructure (Emergency Response Systems, Fire Safety Systems)

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

Environmental and Sustainability Projects (Renewable Energy, Water Conservation, Waste Management)

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

Affordable Housing

Design: 1-2 years
Right-of-Way Acquisition: 6 months – 1 year
Utilities Relocation: 6 months – 1 year
Construction: 1-3 years
Minimum Duration: 3 years
Maximum Duration: 7 years

These total durations are estimates based on the individual stage durations previously provided. They represent a cumulative timeframe that incorporates design, right-of-way acquisition, utilities relocation, and construction. As previously noted, actual durations can vary significantly depending on a multitude of factors specific to each project.

At Front Line Advisory Group, we are pioneers in Capital Improvement Bond Management, leveraging unparalleled expertise and deep industry insights. Our mission extends beyond consultation – we empower our clients to realize the full potential of their investments, ensuring tax dollars are put to maximum use through astute Program Management Consulting. For more information or to commence your journey towards transformative bond management, reach out to us at info@frontlineadvisorygroup.com

FLAG provides program management consulting services in Central Texas for municipal and school capital improvement bonds. FLAG is revolutionizing the construction industry and transforming client expectations by obsessing over the basics of budget oversight, schedule enforcement, compliance, vendor management, and stakeholder communication.

Join our weekly newsletter and receive a free copy of our new book!

JOIN NEWSLETTER

Articles Capital Improvement Programs CIP

The Imperative for a Capital Improvement Program Management Consultant

Capital improvement bond programs, typically a recurring event in government agencies every three to five years, put an additional strain...
Read More
Articles Capital Improvement Programs CIP

Promoting Accountability and Quality Assurance: The Role of a Rating System

Accountability and quality assurance are crucial for successful project delivery in any industry, and capital infrastructure programs are no exception....
Read More
Articles Capital Improvement Programs CIP Local

Continuing Success: Navigating the Next Steps in Georgetown’s Capital Improvement Bond Program

Congratulations are well-deserved for the Georgetown City Council as they successfully progress in shaping the capital improvement bond program. As...
Read More
Articles Change Management Development Services Economic Development

Boosting Economic Development by Improving Permitting Process Speed

The economic development of a region relies heavily on the efficient functioning of its municipalities. One critical factor that influences...
Read More
Articles CIP

When the Clock Ticks and Costs Soar: Decoding Overruns in Capital Improvement Bond Programs

In the world of public finance and infrastructure, capital improvement bond programs represent substantial, often vital commitments to improving our...
Read More
Articles CIP

Ensuring Competence and Expertise: The Role of a Rating System

In the realm of capital infrastructure programs, ensuring the competence and expertise of project managers, engineers, and contractors is vital...
Read More
Articles Process Improvement Technology

Navigating Complexity with Ease: Tools and Technologies for Effective Process Management

Effective process management is essential to the success of your organization, providing benefits such as increased efficiency, improved quality, reduced...
Read More
Articles CIP

Capital Improvement Bonds and Housing Subsidies: A Framework for Supporting Public Servants

The backbone of any thriving community is undoubtedly its public servants, which include first responders, government staff, and teachers. However,...
Read More
Articles CIP

Streamlining Project Selection Process: Enhancing Efficiency and Success

  In a previous article we discussed the “Benefits of Creating a Rating System for Project Managers, Engineers, and Contractors...
Read More
Articles Change Management

Process Management for Municipal Development Services Professionals

Processes are fundamental to our everyday lives, but it can be a challenge to understand how they work. That can...
Read More
1 12 13 14 15 16 19