Share to:

“The best way to predict the future is to create it.” -Peter Drucker

As a capital improvement bond program manager, ensuring the seamless integration of parcel acquisition services with utility coordination is paramount. Effective communication between the right-of-way (ROW) acquisition phase and the utility coordination phase can significantly mitigate delays, reduce costs, and enhance project outcomes. Here are some best practices and insights drawn from recent research and case studies to highlight the importance of this integration.

Importance of Early and Continuous Coordination

Early and continuous coordination between ROW acquisition and utility relocation is critical. Initiating utility coordination early in the project lifecycle, ideally at the design stage, allows for the identification and resolution of potential conflicts before they become critical issues.

For instance, the Minnesota Department of Transportation (MnDOT) developed a new utility coordination process that begins earlier in the design phase, emphasizing accurate identification and early coordination of utilities. This process involves construction and design personnel at an earlier stage, ensuring consistent and uniform application across all projects ​​.

Establishing Clear Communication Channels

Clear and continuous communication with all stakeholders, including utility companies, property owners, and internal project teams, is essential. The Florida Department of Transportation (FDOT) District 5 emphasizes the importance of maintaining forthright communications with impacted stakeholders from the early stages of the project. This approach not only builds trust but also reduces the level of detrimental rumors and misinformation ​​.

Utilizing Advanced Technology for Coordination

Implementing advanced technologies, such as Geographic Information Systems (GIS), can enhance the efficiency of ROW acquisition and utility coordination. A prototype GIS-based tool developed by the Federal Highway Administration (FHWA) integrates environmental hazard analysis and land acquisition estimates, aiding in transportation decision-making by providing a comprehensive overview of potential utility conflicts and ROW needs ​​.

Integrated Project Delivery Methods

Integrated project delivery methods, such as design-build, where design and construction phases are combined into one contract, can streamline the coordination between ROW acquisition and utility relocation. This approach allows tasks to be undertaken in an overlapping manner, providing incentives for contractors to incorporate alternative technical concepts early in the project ​​.

Best Practices in Utility Coordination

MnDOT’s 15-step utility coordination process includes critical steps such as:

  1. Utility identification
  2. Initial utility contact for coordination
  3. Utility design meetings
  4. Utility relocation plan reviews
  5. Utility agreements and reimbursements ​​

This structured approach ensures that utility relocation is planned and executed efficiently, minimizing delays and construction costs.

Case Studies of Effective Coordination

  • Florida DOT: By involving utilities early at the “line and grade” design stage, FDOT allows utilities to assess project impacts and plan accordingly. This early involvement helps avoid last-minute design changes that can cause significant project delays​​.
  • Texas DOT: For the Central Texas Turnpike System (CTTS) project, TxDOT’s approach included 100 percent utility reimbursement tied to a specific project schedule, which expedited utility relocation without the need for state intervention ​​.

Conclusion

Effective coordination between parcel acquisitions and utility relocation requires early planning, continuous communication, the use of advanced technologies, and integrated project delivery methods. By implementing these best practices, project managers can enhance project efficiency, reduce costs, and ensure timely project delivery.

At Front Line Advisory Group, we manage Capital Improvement programs to ensure they are completed on time and within budget. We make sure every dollar is used wisely to improve our community. For more information or to start your project, contact us at info@frontlineadvisorygroup.com.

Bibliography

  • Cambridge Systematics, Inc. (2006). NCHRP 20-68, Domestic Scan Pilot Program: Best Practices in Right-of-Way Acquisition and Utility Relocation. National Cooperative Highway Research Program, Transportation Research Board of the National Academies.

FLAG provides program management consulting services in Central Texas for municipal and school capital improvement bonds. FLAG is revolutionizing the construction industry and transforming client expectations by obsessing over the basics of budget oversight, schedule enforcement, compliance, vendor management, and stakeholder communication.

Join our weekly newsletter and receive a free copy of our new book!

JOIN NEWSLETTER

Articles Bonds Capital Improvement Plan Capital Improvement Programs CIP Planning Schedule Technology

The Importance of Completing Projects on Time and Budget in a Rising Interest Rate Environment

Navigating the Challenges of Completing Projects on Time and Budget in a Rising Interest Rate Environment Completing projects on time...
Read More
Articles Capital Improvement Plan Capital Improvement Programs CIP Planning Technology

2024 Update: Impact of Travis County’s Public Improvement District Policy

Travis County's Public Improvement District Policy Update The 2024 update on Travis County's Public Improvement District Policy has brought about...
Read More
Articles Capital Improvement Plan Capital Improvement Programs CIP Planning Process Improvement Technology

Revolutionizing Capital Improvement: The Impact of Artificial Intelligence

The Role of Artificial Intelligence in Transforming Capital Improvement Bond Programs Artificial intelligence (AI) is revolutionizing capital improvement bond programs...
Read More
Articles Capital Improvement Plan Capital Improvement Programs CIP Planning

Get It Right from the Start or Pay the Price: The Urgent Need for Reform in Capital Improvement Bond Programs

The Importance of Starting Correctly on Capital Improvement Bond Programs Starting correctly on capital improvement bond programs is crucial for...
Read More
Articles Capital Improvement Plan Capital Improvement Programs CIP Planning Process Improvement

Book Review: How Big Things Get Done: The Surprising Factors That Determine the Fate of Every Project

How Big Things Get Done: Unveiling the Secrets of Successful Megaprojects “a whopping 91.5% of projects overshoot budgets or timelines,...
Read More
Articles Capital Improvement Plan Capital Improvement Programs CIP Planning Process Improvement

Read or Risk Ruin: 10 Must-Have Books on Capital Improvement Bonds for Taxpayers and Decision-Makers

Essential Reading for Capital Improvement Bond Program Managers Leading a capital improvement bond program intertwines expertise from public finance to...
Read More
Articles Capital Improvement Plan Capital Improvement Programs CIP Local Planning

Time for a Change in Mindset: Why the Construction Industry Must Mature

In an era where innovation and efficiency are the benchmarks of success, it's baffling that the construction industry still operates...
Read More
Articles Capital Improvement Plan Capital Improvement Programs CIP Local Planning

Avoid These 7 Deadly Sins of Capital Improvement Program Management

Introduction Program managers, project managers, and construction professionals play a crucial role in capital improvement program management. To ensure successful...
Read More
Articles Capital Improvement Plan Capital Improvement Programs CIP Local Planning

Revolutionize Your Capital Project: Control Duration and Costs with Optimization

Navigating the intricate pathways of capital projects is a monumental task, often marked by a relentless race against time. These...
Read More
1 2 3 4 5 6 18