Share to:

“The best way to predict the future is to create it.” -Peter Drucker

As a capital improvement bond program manager, ensuring the seamless integration of parcel acquisition services with utility coordination is paramount. Effective communication between the right-of-way (ROW) acquisition phase and the utility coordination phase can significantly mitigate delays, reduce costs, and enhance project outcomes. Here are some best practices and insights drawn from recent research and case studies to highlight the importance of this integration.

Importance of Early and Continuous Coordination

Early and continuous coordination between ROW acquisition and utility relocation is critical. Initiating utility coordination early in the project lifecycle, ideally at the design stage, allows for the identification and resolution of potential conflicts before they become critical issues.

For instance, the Minnesota Department of Transportation (MnDOT) developed a new utility coordination process that begins earlier in the design phase, emphasizing accurate identification and early coordination of utilities. This process involves construction and design personnel at an earlier stage, ensuring consistent and uniform application across all projects ​​.

Establishing Clear Communication Channels

Clear and continuous communication with all stakeholders, including utility companies, property owners, and internal project teams, is essential. The Florida Department of Transportation (FDOT) District 5 emphasizes the importance of maintaining forthright communications with impacted stakeholders from the early stages of the project. This approach not only builds trust but also reduces the level of detrimental rumors and misinformation ​​.

Utilizing Advanced Technology for Coordination

Implementing advanced technologies, such as Geographic Information Systems (GIS), can enhance the efficiency of ROW acquisition and utility coordination. A prototype GIS-based tool developed by the Federal Highway Administration (FHWA) integrates environmental hazard analysis and land acquisition estimates, aiding in transportation decision-making by providing a comprehensive overview of potential utility conflicts and ROW needs ​​.

Integrated Project Delivery Methods

Integrated project delivery methods, such as design-build, where design and construction phases are combined into one contract, can streamline the coordination between ROW acquisition and utility relocation. This approach allows tasks to be undertaken in an overlapping manner, providing incentives for contractors to incorporate alternative technical concepts early in the project ​​.

Best Practices in Utility Coordination

MnDOT’s 15-step utility coordination process includes critical steps such as:

  1. Utility identification
  2. Initial utility contact for coordination
  3. Utility design meetings
  4. Utility relocation plan reviews
  5. Utility agreements and reimbursements ​​

This structured approach ensures that utility relocation is planned and executed efficiently, minimizing delays and construction costs.

Case Studies of Effective Coordination

  • Florida DOT: By involving utilities early at the “line and grade” design stage, FDOT allows utilities to assess project impacts and plan accordingly. This early involvement helps avoid last-minute design changes that can cause significant project delays​​.
  • Texas DOT: For the Central Texas Turnpike System (CTTS) project, TxDOT’s approach included 100 percent utility reimbursement tied to a specific project schedule, which expedited utility relocation without the need for state intervention ​​.

Conclusion

Effective coordination between parcel acquisitions and utility relocation requires early planning, continuous communication, the use of advanced technologies, and integrated project delivery methods. By implementing these best practices, project managers can enhance project efficiency, reduce costs, and ensure timely project delivery.

At Front Line Advisory Group, we manage Capital Improvement programs to ensure they are completed on time and within budget. We make sure every dollar is used wisely to improve our community. For more information or to start your project, contact us at info@frontlineadvisorygroup.com.

Bibliography

  • Cambridge Systematics, Inc. (2006). NCHRP 20-68, Domestic Scan Pilot Program: Best Practices in Right-of-Way Acquisition and Utility Relocation. National Cooperative Highway Research Program, Transportation Research Board of the National Academies.

FLAG provides program management consulting services in Central Texas for municipal and school capital improvement bonds. FLAG is revolutionizing the construction industry and transforming client expectations by obsessing over the basics of budget oversight, schedule enforcement, compliance, vendor management, and stakeholder communication.

Join our weekly newsletter and receive a free copy of our new book!

JOIN NEWSLETTER

Articles

Understanding MUDs: Municipal Utility Districts

When you drive through the vibrant neighborhoods of Texas, you might wonder how these communities spring to life with essential...
Read More
Articles

Mitigating Risks in Capital Improvement Projects: Lessons from Successful and Failed Projects

Capital Improvement Projects (CIP) are the backbone of infrastructure development, essential for maintaining and enhancing public amenities. These projects, ranging...
Read More
Articles Capital Improvement Plan Change Management Development Services Economic Development Educating Industry Process Improvement

Accelerating Project Delivery

"The road to success is always under construction." -Lily Tomlin   Infrastructure development is a cornerstone of modern society, enabling...
Read More
Articles Educating Industry Process Improvement Public Improvement District

Texas A&M Report: Utilities Best Practices

"An investment in knowledge pays the best interest." -Benjamin Franklin Over the past six years, Front Line Advisory Group (FLAG)...
Read More
Articles Bonds Capital Improvement Plan Capital Improvement Programs Process Improvement

Coordinating Right of Way Acquisitions and Utility Relocation

"The best way to predict the future is to create it." -Peter Drucker As a capital improvement bond program manager,...
Read More
Articles Educating Industry Planning Process Improvement

40 Projects Complete, 6 Years, 5 Hard Lessons

"Lost time is never found again." -Benjamin Franklin Over the past six years, our firm has successfully managed the completion...
Read More
Articles Educating Industry Planning Process Improvement

Smart Strategies for Managing Design Changes in Construction Projects

Efficient Construction Project Management Efficiently overseeing alterations to construction designs is a critical aspect of construction project management. The ability...
Read More
Articles Bonds Capital Improvement Plan Capital Improvement Programs CIP

How to Prioritize Community Projects for a Capital Improvement Bond Package

Prioritizing Community Projects Prioritizing community projects for a capital improvement bond package is a critical endeavor. This guide delves into...
Read More
Articles Capital Improvement Plan Capital Improvement Programs Change Management CIP CIP Budgetting Development Services

The Significance of Municipal Leadership Support for Capital Bond Programs

Understanding Capital Bonds Capital bond programs, also known as municipal bonds or government bonds, are essential financial instruments for funding...
Read More
1 2 3 4 5 6 19