As a capital improvement bond program manager, ensuring the seamless integration of parcel acquisition services with utility coordination is paramount. Effective communication between the right-of-way (ROW) acquisition phase and the utility coordination phase can significantly mitigate delays, reduce costs, and enhance project outcomes. Here are some best practices and insights drawn from recent research and case studies to highlight the importance of this integration.

Importance of Early and Continuous Coordination

Early and continuous coordination between ROW acquisition and utility relocation is critical. Initiating utility coordination early in the project lifecycle, ideally at the design stage, allows for the identification and resolution of potential conflicts before they become critical issues.

For instance, the Minnesota Department of Transportation (MnDOT) developed a new utility coordination process that begins earlier in the design phase, emphasizing accurate identification and early coordination of utilities. This process involves construction and design personnel at an earlier stage, ensuring consistent and uniform application across all projects ​​.

Establishing Clear Communication Channels

Clear and continuous communication with all stakeholders, including utility companies, property owners, and internal project teams, is essential. The Florida Department of Transportation (FDOT) District 5 emphasizes the importance of maintaining forthright communications with impacted stakeholders from the early stages of the project. This approach not only builds trust but also reduces the level of detrimental rumors and misinformation ​​.

Utilizing Advanced Technology for Coordination

Implementing advanced technologies, such as Geographic Information Systems (GIS), can enhance the efficiency of ROW acquisition and utility coordination. A prototype GIS-based tool developed by the Federal Highway Administration (FHWA) integrates environmental hazard analysis and land acquisition estimates, aiding in transportation decision-making by providing a comprehensive overview of potential utility conflicts and ROW needs ​​.

Integrated Project Delivery Methods

Integrated project delivery methods, such as design-build, where design and construction phases are combined into one contract, can streamline the coordination between ROW acquisition and utility relocation. This approach allows tasks to be undertaken in an overlapping manner, providing incentives for contractors to incorporate alternative technical concepts early in the project ​​.

Best Practices in Utility Coordination

MnDOT’s 15-step utility coordination process includes critical steps such as:

  1. Utility identification
  2. Initial utility contact for coordination
  3. Utility design meetings
  4. Utility relocation plan reviews
  5. Utility agreements and reimbursements ​​

This structured approach ensures that utility relocation is planned and executed efficiently, minimizing delays and construction costs.

Case Studies of Effective Coordination

  • Florida DOT: By involving utilities early at the “line and grade” design stage, FDOT allows utilities to assess project impacts and plan accordingly. This early involvement helps avoid last-minute design changes that can cause significant project delays​​.
  • Texas DOT: For the Central Texas Turnpike System (CTTS) project, TxDOT’s approach included 100 percent utility reimbursement tied to a specific project schedule, which expedited utility relocation without the need for state intervention ​​.

Conclusion

Effective coordination between parcel acquisitions and utility relocation requires early planning, continuous communication, the use of advanced technologies, and integrated project delivery methods. By implementing these best practices, project managers can enhance project efficiency, reduce costs, and ensure timely project delivery.

At Front Line Advisory Group, we manage Capital Improvement programs to ensure they are completed on time and within budget. We make sure every dollar is used wisely to improve our community. For more information or to start your project, contact us at info@frontlineadvisorygroup.com.

Bibliography

  • Cambridge Systematics, Inc. (2006). NCHRP 20-68, Domestic Scan Pilot Program: Best Practices in Right-of-Way Acquisition and Utility Relocation. National Cooperative Highway Research Program, Transportation Research Board of the National Academies.

FLAG provides program management consulting services in Central Texas for municipal and school capital improvement bonds. FLAG is revolutionizing the construction industry and transforming client expectations by obsessing over the basics of budget oversight, schedule enforcement, compliance, vendor management, and stakeholder communication.

Join our weekly newsletter and receive a free copy of our new book!

JOIN NEWSLETTER

How Front Line Advisory Group Program-Level Controls Save Local Governments Money
Articles

How Front Line Advisory Group Program-Level Controls Save Local Governments Money

Executive Summary: Front Line Advisory Group (FLAG) applies disciplined program management to public capital projects, enabling local governments to avoid...
Read More
Why Texas Infrastructure Bond Votes Often Stumble
Articles

Why Texas Infrastructure Bond Votes Often Stumble

In cities and counties across Texas, local leaders are asking voters to approve billions in debt for roads, bridges, water...
Read More
Richardson’s $200 Million Vision: Building a More Resilient, Connected City
Articles

Richardson’s $200 Million Vision: Building a More Resilient, Connected City

The City of Richardson is preparing to launch an ambitious $200 million bond program anticipated for May 2026, representing a...
Read More
Building Beaumont’s Future: A $264 Million Bond to Strengthen Infrastructure, Safety, and Community Life
Articles

Building Beaumont’s Future: A $264 Million Bond to Strengthen Infrastructure, Safety, and Community Life

The City of Beaumont is preparing for a major investment in its future. On November 4, 2025, residents will vote...
Read More
Parker County’s $286 Million Bond Proposal: Investing in Justice, Safety, and Long-Term Growth
Articles

Parker County’s $286 Million Bond Proposal: Investing in Justice, Safety, and Long-Term Growth

Parker County, one of the fastest-growing regions in Texas, is preparing for a pivotal vote this November. On November 4,...
Read More
Billions on the Ballot: America’s Bond Boom and the Push for Accountability
Articles

Billions on the Ballot: America’s Bond Boom and the Push for Accountability

“Whenever the people are well informed, they can be trusted with their own government; … they may be relied on...
Read More
Hood County Weighs a $717 Million Road Program. The Real Work Starts Now.
Articles

Hood County Weighs a $717 Million Road Program. The Real Work Starts Now.

“Give me six hours to chop down a tree and I will spend the first four sharpening the axe.” —...
Read More
The Two Sides of the Scheduling Coin: Primavera P6 vs. Microsoft Project
Articles

The Two Sides of the Scheduling Coin: Primavera P6 vs. Microsoft Project

“Plans are nothing; planning is everything.” — Dwight D. Eisenhower   At a massive highway construction site in Texas, engineers...
Read More
Building Before the Boom
Articles

Building Before the Boom

“The time to repair the roof is when the sun is shining.” — John F. Kennedy Building Ahead of the...
Read More
AI and Standardization: Transforming Capital Bond Program Controls
Articles

AI and Standardization: Transforming Capital Bond Program Controls

AI and Standardization: Transforming Capital Bond Program Controls for Success and Trust Capital improvement bond programs are massive undertakings –...
Read More
1 2 3 25