Share to:

“The best way to predict the future is to create it.” -Peter Drucker

As a capital improvement bond program manager, ensuring the seamless integration of parcel acquisition services with utility coordination is paramount. Effective communication between the right-of-way (ROW) acquisition phase and the utility coordination phase can significantly mitigate delays, reduce costs, and enhance project outcomes. Here are some best practices and insights drawn from recent research and case studies to highlight the importance of this integration.

Importance of Early and Continuous Coordination

Early and continuous coordination between ROW acquisition and utility relocation is critical. Initiating utility coordination early in the project lifecycle, ideally at the design stage, allows for the identification and resolution of potential conflicts before they become critical issues.

For instance, the Minnesota Department of Transportation (MnDOT) developed a new utility coordination process that begins earlier in the design phase, emphasizing accurate identification and early coordination of utilities. This process involves construction and design personnel at an earlier stage, ensuring consistent and uniform application across all projects ​​.

Establishing Clear Communication Channels

Clear and continuous communication with all stakeholders, including utility companies, property owners, and internal project teams, is essential. The Florida Department of Transportation (FDOT) District 5 emphasizes the importance of maintaining forthright communications with impacted stakeholders from the early stages of the project. This approach not only builds trust but also reduces the level of detrimental rumors and misinformation ​​.

Utilizing Advanced Technology for Coordination

Implementing advanced technologies, such as Geographic Information Systems (GIS), can enhance the efficiency of ROW acquisition and utility coordination. A prototype GIS-based tool developed by the Federal Highway Administration (FHWA) integrates environmental hazard analysis and land acquisition estimates, aiding in transportation decision-making by providing a comprehensive overview of potential utility conflicts and ROW needs ​​.

Integrated Project Delivery Methods

Integrated project delivery methods, such as design-build, where design and construction phases are combined into one contract, can streamline the coordination between ROW acquisition and utility relocation. This approach allows tasks to be undertaken in an overlapping manner, providing incentives for contractors to incorporate alternative technical concepts early in the project ​​.

Best Practices in Utility Coordination

MnDOT’s 15-step utility coordination process includes critical steps such as:

  1. Utility identification
  2. Initial utility contact for coordination
  3. Utility design meetings
  4. Utility relocation plan reviews
  5. Utility agreements and reimbursements ​​

This structured approach ensures that utility relocation is planned and executed efficiently, minimizing delays and construction costs.

Case Studies of Effective Coordination

  • Florida DOT: By involving utilities early at the “line and grade” design stage, FDOT allows utilities to assess project impacts and plan accordingly. This early involvement helps avoid last-minute design changes that can cause significant project delays​​.
  • Texas DOT: For the Central Texas Turnpike System (CTTS) project, TxDOT’s approach included 100 percent utility reimbursement tied to a specific project schedule, which expedited utility relocation without the need for state intervention ​​.

Conclusion

Effective coordination between parcel acquisitions and utility relocation requires early planning, continuous communication, the use of advanced technologies, and integrated project delivery methods. By implementing these best practices, project managers can enhance project efficiency, reduce costs, and ensure timely project delivery.

At Front Line Advisory Group, we manage Capital Improvement programs to ensure they are completed on time and within budget. We make sure every dollar is used wisely to improve our community. For more information or to start your project, contact us at info@frontlineadvisorygroup.com.

Bibliography

  • Cambridge Systematics, Inc. (2006). NCHRP 20-68, Domestic Scan Pilot Program: Best Practices in Right-of-Way Acquisition and Utility Relocation. National Cooperative Highway Research Program, Transportation Research Board of the National Academies.

FLAG provides program management consulting services in Central Texas for municipal and school capital improvement bonds. FLAG is revolutionizing the construction industry and transforming client expectations by obsessing over the basics of budget oversight, schedule enforcement, compliance, vendor management, and stakeholder communication.

Join our weekly newsletter and receive a free copy of our new book!

JOIN NEWSLETTER

Articles Capital Improvement Programs

Mitigating Inflationary Risks in Capital Improvement Bond Programs

Mitigating Inflationary Risks in Capital Improvement Bond Programs: A Guide for Local Governments and ISDs As the need for additional...
Read More
Articles Capital Improvement Programs

The Latest Trends in Capital Improvement Bond Programs: A Comprehensive Guide

Capital improvement bond programs are a vital tool of modern infrastructure investment. These programs provide communities with the funds they...
Read More
Articles School Bonds

Making an Informed Choice

School Bond Details Every Voter Should Know What is the purpose of your school bond, and the implication of it...
Read More
Articles Development Services

Growing Pains: Solving Administrative Challenges in Central Texas Municipalities

Municipalities in Central Texas have been experiencing explosive growth for over a decade, leading to infrastructure strain, housing issues, traffic...
Read More
Articles School Bonds

Developing a Capital Improvement Bond for Building Schools: What Taxpayers Should Ask

A capital improvement bond is a type of bond that is used to fund large-scale projects, such as building new...
Read More
Articles Educating Industry

What Skills and Qualifications are Required of a Program Management Consultant Firm on a Capital Improvement Bond Program?

The success of a Capital Improvement Bond (CIB) program depends not only on the technical expertise and experience of the...
Read More
Articles School Bonds

Building for the Future

An Introduction to School Bonds What is a school bond? School districts issue bonds to raise funds for various capital...
Read More
Articles Educating Taxpayer

What is a Capital Improvement Bond Program?

A Capital Improvement Bond Program is a financing tool used by governments to fund major infrastructure projects and upgrades. This...
Read More
Articles Capital Improvement Programs

What is the role of a Program Management Consultant in a Capital Improvement Bond Program?

Capital improvement bond programs are massive endeavors, with numerous projects, stakeholders, and deadlines. The key to ensuring that everything goes...
Read More
Articles School Bonds

Building Better Schools on a Budget

The Most Affordable Methods The size, type of building, location, and cost of materials and labor impact the cost of...
Read More
1 17 18 19