Share to:

“The best way to predict the future is to create it.” -Peter Drucker

As a capital improvement bond program manager, ensuring the seamless integration of parcel acquisition services with utility coordination is paramount. Effective communication between the right-of-way (ROW) acquisition phase and the utility coordination phase can significantly mitigate delays, reduce costs, and enhance project outcomes. Here are some best practices and insights drawn from recent research and case studies to highlight the importance of this integration.

Importance of Early and Continuous Coordination

Early and continuous coordination between ROW acquisition and utility relocation is critical. Initiating utility coordination early in the project lifecycle, ideally at the design stage, allows for the identification and resolution of potential conflicts before they become critical issues.

For instance, the Minnesota Department of Transportation (MnDOT) developed a new utility coordination process that begins earlier in the design phase, emphasizing accurate identification and early coordination of utilities. This process involves construction and design personnel at an earlier stage, ensuring consistent and uniform application across all projects ​​.

Establishing Clear Communication Channels

Clear and continuous communication with all stakeholders, including utility companies, property owners, and internal project teams, is essential. The Florida Department of Transportation (FDOT) District 5 emphasizes the importance of maintaining forthright communications with impacted stakeholders from the early stages of the project. This approach not only builds trust but also reduces the level of detrimental rumors and misinformation ​​.

Utilizing Advanced Technology for Coordination

Implementing advanced technologies, such as Geographic Information Systems (GIS), can enhance the efficiency of ROW acquisition and utility coordination. A prototype GIS-based tool developed by the Federal Highway Administration (FHWA) integrates environmental hazard analysis and land acquisition estimates, aiding in transportation decision-making by providing a comprehensive overview of potential utility conflicts and ROW needs ​​.

Integrated Project Delivery Methods

Integrated project delivery methods, such as design-build, where design and construction phases are combined into one contract, can streamline the coordination between ROW acquisition and utility relocation. This approach allows tasks to be undertaken in an overlapping manner, providing incentives for contractors to incorporate alternative technical concepts early in the project ​​.

Best Practices in Utility Coordination

MnDOT’s 15-step utility coordination process includes critical steps such as:

  1. Utility identification
  2. Initial utility contact for coordination
  3. Utility design meetings
  4. Utility relocation plan reviews
  5. Utility agreements and reimbursements ​​

This structured approach ensures that utility relocation is planned and executed efficiently, minimizing delays and construction costs.

Case Studies of Effective Coordination

  • Florida DOT: By involving utilities early at the “line and grade” design stage, FDOT allows utilities to assess project impacts and plan accordingly. This early involvement helps avoid last-minute design changes that can cause significant project delays​​.
  • Texas DOT: For the Central Texas Turnpike System (CTTS) project, TxDOT’s approach included 100 percent utility reimbursement tied to a specific project schedule, which expedited utility relocation without the need for state intervention ​​.

Conclusion

Effective coordination between parcel acquisitions and utility relocation requires early planning, continuous communication, the use of advanced technologies, and integrated project delivery methods. By implementing these best practices, project managers can enhance project efficiency, reduce costs, and ensure timely project delivery.

At Front Line Advisory Group, we manage Capital Improvement programs to ensure they are completed on time and within budget. We make sure every dollar is used wisely to improve our community. For more information or to start your project, contact us at info@frontlineadvisorygroup.com.

Bibliography

  • Cambridge Systematics, Inc. (2006). NCHRP 20-68, Domestic Scan Pilot Program: Best Practices in Right-of-Way Acquisition and Utility Relocation. National Cooperative Highway Research Program, Transportation Research Board of the National Academies.

FLAG provides program management consulting services in Central Texas for municipal and school capital improvement bonds. FLAG is revolutionizing the construction industry and transforming client expectations by obsessing over the basics of budget oversight, schedule enforcement, compliance, vendor management, and stakeholder communication.

Join our weekly newsletter and receive a free copy of our new book!

JOIN NEWSLETTER

Articles Bonds Capital Improvement Programs Planning Process Improvement

How Chesterfield Improved Their Bond Rating & Lessons for Other Local Governments

In the ever-evolving financial landscape of local governments, Chesterfield Township has achieved a commendable feat: a credit rating upgrade. With...
Read More
Articles Capital Improvement Programs Planning PMC Program Management Consultants

How Program Management Consultants Save Money for Local Governments

Introduction Program management consultants play a crucial role in helping local governments save money on capital infrastructure bond programs. These...
Read More
Articles Capital Improvement Programs CIP

The Dual-Edged Sword of Inflation: Navigating Its Impacts on Capital Improvement Bond Programs

In the ever-evolving realm of capital improvement bond programs, inflation emerges as a pivotal factor, wielding a double-edged influence. For...
Read More
Articles Uncategorized

Strategic Separation: The Merits of Distinct Program Management Consultant (PMC) and General Engineering Consultant (GEC) Roles

In capital improvement bond programs, distinctly separating the roles of the Program Management Consultant (PMC) and the General Engineering Consultant...
Read More
Articles Capital Improvement Programs CIP Planning

Strategies to Stay Proactive in Addressing the Four Financial Pillars of Capital Improvement Bond Programs

Capital improvement bond programs serve as pivotal financial mechanisms to propel large-scale projects and vital infrastructure developments forward. At the...
Read More
Articles Capital Improvement Programs CIP Planning

Understanding Capital Infrastructure Bond Programs and Their Scope

A capital infrastructure bond program operates as a paramount financial instrument, frequently utilized by public entities, including municipalities. Its function...
Read More
Articles Capital Improvement Programs CIP Planning

Creating a Capital Improvement Bond: A Strategic Guide for Successful Approval

When it comes to establishing a capital improvement bond that stands the best chance of garnering voter approval, it's not...
Read More
Articles Capital Improvement Programs CIP CIP Budgetting Planning Schedule

The Primacy of the Program Master Schedule in a Capital Improvement Bond Program

In the vast expanse of project management, especially in the domain of capital improvement bond programs, there arises a crucial...
Read More
Articles Capital Improvement Programs Planning Process Improvement

The Expansive Role of an Owner’s Representative

An Owner's Representative typically provides a broader range of services than a traditional construction manager, making them invaluable in scenarios...
Read More
Articles Development Services ISD Planning School Bonds

The Critical Questions Every School Board Director Should Ask When Selecting a Program Management Consultant

Selecting the right program management consultant for a school bond construction program is no small feat, especially when it's in...
Read More
1 6 7 8 9 10 19