Share to:

“The best way to predict the future is to create it.” -Peter Drucker

As a capital improvement bond program manager, ensuring the seamless integration of parcel acquisition services with utility coordination is paramount. Effective communication between the right-of-way (ROW) acquisition phase and the utility coordination phase can significantly mitigate delays, reduce costs, and enhance project outcomes. Here are some best practices and insights drawn from recent research and case studies to highlight the importance of this integration.

Importance of Early and Continuous Coordination

Early and continuous coordination between ROW acquisition and utility relocation is critical. Initiating utility coordination early in the project lifecycle, ideally at the design stage, allows for the identification and resolution of potential conflicts before they become critical issues.

For instance, the Minnesota Department of Transportation (MnDOT) developed a new utility coordination process that begins earlier in the design phase, emphasizing accurate identification and early coordination of utilities. This process involves construction and design personnel at an earlier stage, ensuring consistent and uniform application across all projects ​​.

Establishing Clear Communication Channels

Clear and continuous communication with all stakeholders, including utility companies, property owners, and internal project teams, is essential. The Florida Department of Transportation (FDOT) District 5 emphasizes the importance of maintaining forthright communications with impacted stakeholders from the early stages of the project. This approach not only builds trust but also reduces the level of detrimental rumors and misinformation ​​.

Utilizing Advanced Technology for Coordination

Implementing advanced technologies, such as Geographic Information Systems (GIS), can enhance the efficiency of ROW acquisition and utility coordination. A prototype GIS-based tool developed by the Federal Highway Administration (FHWA) integrates environmental hazard analysis and land acquisition estimates, aiding in transportation decision-making by providing a comprehensive overview of potential utility conflicts and ROW needs ​​.

Integrated Project Delivery Methods

Integrated project delivery methods, such as design-build, where design and construction phases are combined into one contract, can streamline the coordination between ROW acquisition and utility relocation. This approach allows tasks to be undertaken in an overlapping manner, providing incentives for contractors to incorporate alternative technical concepts early in the project ​​.

Best Practices in Utility Coordination

MnDOT’s 15-step utility coordination process includes critical steps such as:

  1. Utility identification
  2. Initial utility contact for coordination
  3. Utility design meetings
  4. Utility relocation plan reviews
  5. Utility agreements and reimbursements ​​

This structured approach ensures that utility relocation is planned and executed efficiently, minimizing delays and construction costs.

Case Studies of Effective Coordination

  • Florida DOT: By involving utilities early at the “line and grade” design stage, FDOT allows utilities to assess project impacts and plan accordingly. This early involvement helps avoid last-minute design changes that can cause significant project delays​​.
  • Texas DOT: For the Central Texas Turnpike System (CTTS) project, TxDOT’s approach included 100 percent utility reimbursement tied to a specific project schedule, which expedited utility relocation without the need for state intervention ​​.

Conclusion

Effective coordination between parcel acquisitions and utility relocation requires early planning, continuous communication, the use of advanced technologies, and integrated project delivery methods. By implementing these best practices, project managers can enhance project efficiency, reduce costs, and ensure timely project delivery.

At Front Line Advisory Group, we manage Capital Improvement programs to ensure they are completed on time and within budget. We make sure every dollar is used wisely to improve our community. For more information or to start your project, contact us at info@frontlineadvisorygroup.com.

Bibliography

  • Cambridge Systematics, Inc. (2006). NCHRP 20-68, Domestic Scan Pilot Program: Best Practices in Right-of-Way Acquisition and Utility Relocation. National Cooperative Highway Research Program, Transportation Research Board of the National Academies.

FLAG provides program management consulting services in Central Texas for municipal and school capital improvement bonds. FLAG is revolutionizing the construction industry and transforming client expectations by obsessing over the basics of budget oversight, schedule enforcement, compliance, vendor management, and stakeholder communication.

Join our weekly newsletter and receive a free copy of our new book!

JOIN NEWSLETTER

Articles Capital Improvement Programs CIP CIP Budgetting

Effective Planning: El Paso County’s Consideration of a $200 Million Bond Program

Navigating the intricate dynamics of public infrastructure development often requires a careful blend of foresight, strategy, and community engagement. A...
Read More
Articles Capital Improvement Programs CIP CIP Budgetting

What is a Capital Improvement Program Readiness Audit (CIPRA)

The requirement for a Capital Improvement Program Readiness Audit (CIPRA), while not universally mandated, is of paramount importance to ensure...
Read More
Articles Capital Improvement Programs CIP CIP Budgetting Local

Understanding the Difference Between Critical Path and Driving Path in Project Schedules

Project management involves meticulous planning and scheduling to ensure the successful completion of a project within the allotted time frame....
Read More
Articles Capital Improvement Programs CIP CIP Budgetting

Going Beyond Finance: The Need for Comprehensive Preapproval Processes for Bond Underwriters in High-Growth Municipalities and Independent School Districts

Public finance is an intricate and multi-faceted domain. Its complexity becomes pronounced when we consider the case of bond underwriters...
Read More
Articles Local

Texas: A 5 Year Examination of the Bonds Issued by ISDs and Local Governments

Over the course of the past five years (The period is November 2018 - May 2023), Texas has seen local...
Read More
Articles Local

How to incorporate AI into the Budget Process: A focus on Local Governments

Incorporating artificial intelligence (AI) into the budgeting process in local governments can greatly enhance efficiency, accuracy, and informed decision-making. This...
Read More
Articles Bonds ISD School Bonds

The Changing Landscape of School District Bond Propositions

In the intricate labyrinth of legislation, changes to bond propositions have introduced new complexities for school districts, specifically in how...
Read More
Articles Change Management

Unfreezing the Status Quo

Strategies for Implementing the Unfreeze Phase of Change Management Change is a constant in today's rapidly evolving business landscape. Organizations...
Read More
Articles Capital Improvement Programs CIP

A Prerequisite for Progress: The importance of a Readiness Audit for Capital Improvement Bond Programs

As financial stewards of taxpayers' dollars, local government entities and educational institutions have a solemn duty towards citizens to ensure...
Read More
Articles CIP CIP Budgetting

Understanding the Bonds: Voter-Approved vs. Certificates of Obligation

The world of municipal financing can often be complex, but it is vital for taxpayers to understand the key differences...
Read More
1 9 10 11 12 13 18